Estimation of capital: Difference between revisions
Line 21: | Line 21: | ||
==Estimating Installed Costs: The Factorial Method== | ==Estimating Installed Costs: The Factorial Method== | ||
Before the chemical plants can be built, capital cost estimates must be made. This is done by using the factorial method. Accuracy and the reliability of the estimate will heavily depend on the availability of the data and the level of the design at the time. Lang proposed capital cost equipment by given equation: | |||
C = F * Sum(C_e) | |||
C is the total capital cost, F is the installation factor also known as Lang factor, and C_e is the cost of major equipment. Lang factor is 3.1 for solid processing plant and 4.74 for fluids processing plant. Better estimate can be made when the different factors are used for corresponding equipment. Lang factor for different equipment can be found in calibrated data chart. | |||
Usually, the above method is used as a preliminary estimate. When more detail has been acquired, installation factor are more rigorously estimated. In detailed factorial estimates, other direct costs are compounded into the Lang factor. Installation factors are usually based on a specific material for its equipment, usually carbon steel. Failure to properly correct installation factors for materials of construction is one of the most common sources of error with the factorial method. Material factor, however, does not linearly scale with the installation factor since the transportation cost, labor cost, and fabricator’s cost does not scale with the material of the equipment. Many variations of the factorial method exist as different assumptions can be made which will determine the rigorousness and the accuracy of the estimate. | |||
==Cost Escalation== | ==Cost Escalation== |
Revision as of 05:31, 10 February 2014
Authors: Alex Chandel, Eric Jiang, Minwook Kim, Todor Kukushliev, William Lassman (ChE 352 in Winter 2014)
Steward: David Chen, Fengqi You
Date Presented: 2/9/2014
Introduction
Components of Capital Cost
Accuracy and purpose of Capital Cost Estimates
Order of Magnitude Estimates
Estimating Purchased Equipment Costs
Estimating Installed Costs: The Factorial Method
Before the chemical plants can be built, capital cost estimates must be made. This is done by using the factorial method. Accuracy and the reliability of the estimate will heavily depend on the availability of the data and the level of the design at the time. Lang proposed capital cost equipment by given equation:
C = F * Sum(C_e)
C is the total capital cost, F is the installation factor also known as Lang factor, and C_e is the cost of major equipment. Lang factor is 3.1 for solid processing plant and 4.74 for fluids processing plant. Better estimate can be made when the different factors are used for corresponding equipment. Lang factor for different equipment can be found in calibrated data chart. Usually, the above method is used as a preliminary estimate. When more detail has been acquired, installation factor are more rigorously estimated. In detailed factorial estimates, other direct costs are compounded into the Lang factor. Installation factors are usually based on a specific material for its equipment, usually carbon steel. Failure to properly correct installation factors for materials of construction is one of the most common sources of error with the factorial method. Material factor, however, does not linearly scale with the installation factor since the transportation cost, labor cost, and fabricator’s cost does not scale with the material of the equipment. Many variations of the factorial method exist as different assumptions can be made which will determine the rigorousness and the accuracy of the estimate.
Cost Escalation
Location Factors
Because of the abundance of chemical engineering plants in the U.S Gulf Coast, it is often the standard for plant and equipment cost. Cost of plant construction will differ based on:
- Construction Infrastructure
- Labor costs
- Transportation costs
- Tax Rates
- Exchange Rates
It is common to convert cost of construction to locations other than the U.S. Gulf Coast by applying a location factor in which:
Estimating Offsite Capital Costs
Computer Tools for Cost Estimating
Validity of Cost Estimates
References
1. Gavin Towler and Ray Sinnott, Chapter 7 – Capital Cost Estimating, Chemical Engineering Design, 2nd Ed., edited by Gavin Towler and Ray Sinnott, Butterworth-Heinemann, Boston, 2013, Pages 307–354, ISBN 9780080966595, http://www.sciencedirect.com/science/article/pii/B9780080966595000079.